Baha Mar Cooling Line

ISD was subcontracted in the amount of $3,000,000

ISD was subcontracted by CCA Bahamas Ltd. to install HDPE pipework from the supply wells to the Central Utility Plant building, and then to the disposal wells for heat rejection for the entire Baha Mar development (circa 34MW). Works included installation of 3,300ft of HDPE cooling water main (sizes ranged from 20″ to 48″, butt fusion), 11,500ft of PVC electrical ducts (from 2″ to 6″), concrete well chambers, 2 vertical turbine pumps (650 litres/ second), and 750kVA transformers and VFD’s.