ISD was contracted to carry out the following scope of works for the development of the tourist destination island, CocoCay. Works included:
Heavy earthworks
Construction of various concrete and wood buildings/structures, including:
o Back of house facilities such as the generator building, commissary building, waste water treatment plant, staff housing, etc., of various sizes ranging from 200–15,000 square feet.
o Front of house restaurants and tourist facilities
o Concrete foundation/bases for the slides and light bases
Installation of all utilities for the site including potable water, sewer, drainage, electrical and telecommunications.
Construction of port facility for island.
Demolition of existing structures to accommodate new structures.
Installation of 3no. 2 MegaWatt Generators to power the entire island.
Installation of site wide utilities.
Construction of structural elements throughout the entire site, including concrete foundations, walls, etc.